Mechanical, Civil and Structural Detailed Design

EPES were engaged by Zinfra as Sydney Waters D&C contractor for the design and construction of SP1197 sewerage pumping station, pressure main and receiving gravity sewer at Emerald Hills in the South West Growth Centre, Leppington NSW.

Design package included:

​1. 71L/s Sewage pumping station consisting of two sets of submersible pumps, precast wet well, valve chamber, inlet maintenance hole, outdoor electrical kiosk, bypass pumping arrangement, emergency storage tank, chemical dosing unit and associated works

2. Pressure main consisting of 1,130m of DN315 HDPE pipe including scours, jetting points and associated works

Project Information

Location: South West Growth Centre, Leppington, New South Wales, Australia
Client: Zinfra c/o Sydney Water
Engagement: Detailed Design Consultant
Sectors: Industrial, Water and Waste Water
Services: Construction and Design Consulting, Digital Engineering, Infrastructure Engineering, Piping Engineering, Water and Waste Water
Year: 2015-2017

3. Receiving gravity sewer consisting of 1,770m of DN355 HDPE pipe draining to the receiving maintenance hole

The scope of the works included all mechanical, civil and structural design elements including development of various approval documentation including Design Management Plans, Safety in Design, CHAIR, FMECA and various design reviews with Sydney Water management and operations teams.

Design deliverables were prepared following tendered Concept Design through 30% and 80% Detailed Design, Workshop Coordination and Works-as-Constructed (as Approved by Sydney Water). Site inspections during construction.

The Problem

Several challenges were identified during the design delivery effort, such as:

We were also tasked with ensuring that the information we produced was coherent, organised and in a suitable format to be integrated into AFMOnline.

Analysis and Implementation

Ongoing and regular communication with stakeholders enabled issues to be raised as early as possible, with an agreed path to resolution. Identifying key concerns and risks in the design enabled the design to take a pragmatic approach with buy-in.

Outcome

The project has been operational since 2017 with no technical issues identified.

Using experienced technical staff and ensuring that communication channels are always open presents an opportunity to deliver a challenging project with final acceptance. Long term reliable operation follows diligent design.

WestConnex – M4-M5 Link

WestConnex – M4-M5 Link Slide 1
previous arrowprevious arrow
next arrownext arrow

WestConnex - M4-M5 Link

Pressurised Services and Dewatering Concept Strategy

The M4-M5 link is part of the WestConnex project in Sydney and involves the construction of twin 7.5km tunnels to link the new M4 at Haberfield and the new M5 at St Peters. EPES were engaged by LSBJV to perform conceptual design methodology for installation of pressurised temporary services for use during construction.

​1. Dewatering systems

2. Compressed air

3. Industrial water

The works include the determination of installation, testing, inspection and maintenance requirements for the pressurised services systems, as well as nominating pumps, piping and valving requirements.

Project Information

Location: Sydney, New South Wales, Australia
Client: Lend Lease, Samsung, Bouygues Joint Venture (LSBJV)
Engagement: Temporary Works Design Engineer
Sectors: Industrial, Road Infrastructure (Tunnels)
Services: Construction and Design Consulting, Independent Reviews and Audits, Infrastructure Engineering, Piping Engineering, Specialist Analysis, Water and Waste Water
Year: 2019

The Problem

Pressurised services are complex on large construction projects and can be high risk in the event of a failure. They can also be highly problematic for construction works if they do not perform as required by the demands of the construction process.

Recognising the size and complexity of this project, as well as a need to ensure consistency across the various construction fronts, the objective of this design was to collate and coordinate all of the variable pieces of information and perspectives and achieve a common approach to pressurised services installation.  

Analysis and Implementation

Several meetings with stakeholders in design, project management, construction and procurement were undertaken to collate the different ideas and information associated with the works. Design documents were developed, along with robust and practical engineering design to ensure consistency, standardisation and a clear path toward compliance with standards.

Outcome

Through this process significant commercial advantages were achieved through standardisation and sharing of plant and equipment, enabling early ordering of piping and valves and exploiting the opportunities of economies of scale. 

Undertaking early planning and design concept development, as well as opening communication with various stakeholders early in the project life cycle there are significant commercial benefits as well as reduced level of risk.

Melbourne Metro – Tunnel

Melbourne Metro – Tunnel Slide 1
previous arrowprevious arrow
next arrownext arrow

Melbourne Metro Tunnel

Temporary Works Engineering Packages

EPES were engaged by CYP to undertake various design packages related to temporary works during construction, including:

​1. Concept design and planning assistance for pressurised services (dewatering, compressed air, recycled water and potable water) used in excavation works at the CBD North and South zones (covering 8 shafts and interconnecting tunnels)

2. Engineering design for adit and cavern hooks, cross over supports and shaft brackets, and verification of shaft service ladders and top shaft brackets

Generally, design packages incorporated engineering analysis, reviews for constructability, safety in design and coordination with construction teams to ensure that design was in alignment with site expectations.

Project Information

Location: Melbourne, Victoria, Australia
Client: Cross Yarra Partnership (CYP)
Engagement: Engineering Consultant
Sectors: Industrial, Rail Infrastructure (Tunnels)
Services: Construction and Design Consulting, Independent Reviews and Audits, Infrastructure Engineering, Piping Engineering, Specialist Analysis, Water and Waste Water
Year: 2019

The Problem

Pressurised services are complex on large construction projects and can be high risk in the event of a failure. Identifying the correct design loadings, as well as risks associated with operation in a live construction environment were considered in the engineering analysis. Relative conservatism is this type of design package is pragmatic, whilst understanding the temporary nature of the works.

Analysis and Implementation

EPES performed analysis is accordance with the mandated standards and codes such as AS1170 for loading, AS4041 for pressure piping and AS4100 for steel structures. Close consultation with site construction enabled coordination with actual installation constraints as well as a means of clarifying design cases, limitations and risks. 

Outcome

The outcome was a comprehensive design package with appropriate levels of buy in from temporary works managers, site teams and procurement. Design documents were prepared well ahead of the being required for site works which enabled proper planning to be undertaken and communication to respective site personnel.

Well organised and planned design work dramatically reduces both technical, safety and commercial risks for all stakeholders on a project.  

8LWR Seismic Analysis, Water Treatment Facility, New Zealand

8LWR Seismic Analysis, Water Treatment Facility, Waikari, New Zealand Slide 1
previous arrowprevious arrow
next arrownext arrow

8LWR Seismic Analysis, Water Treatment Facility, Waikari, New Zealand

Mechanical Structural Analysis

EPES were engaged by Pall Australia to perform an earthquake loading analysis of the 8LWR structure designed by Pall for support of water treatment equipment in the Waikari region of New Zealand.

Analysis was performed in accordance with NZS 1170.5 Earthquake Actions New Zealand and AS/NZS 4100 Steel Structures. The water treatment facility is required to remain operational following an earthquake with a design life of 80 years.

EPES were to determine of the structure would satisfy the standards requirements for seismic loading in this region.

Project Information

Location: Waikari, New Zealand
Client: Pall Australia
Engagement: Specialist Finite Element Analysis
Sectors: Industrial, Water and Waste Water
Services: Construction and Design Consulting, Digital Engineering, Infrastructure Engineering, Piping Engineering, Specialist Analysis, Water and Waste Water
Year: 2019

The Problem

The region has high seismic activity and high design loadings were calculated due to the stringent requirements of NZS 1170.5 and the requirement for the water treatment facility to remain in operation shortly after a design seismic event. 

Analysis and Implementation

EPES utilised AS/NZS 1170.0 and AS1170.1 to determine design loadings for the proposed VR structure and MF module rack assembly. Design analysis was undertaken following NZS 1170.5 and application of Finite Element Analysis (FEA) using SolidWorks.   

Analysis determined that for the MF Rack Assembly, higher than acceptable deflections were evident in the analysis and that in order to satisfy the design criteria, additional bracing was recommended.  The VR frame was within acceptable limits.

Outcome

We identified deficiencies in the designed structure and methods required to rectify in order to achieve compliance with the local New Zealand earthquake design requirements. This was validated using Finite Element Analysis (FEA).